Africa
Since 1959, the Berger Group has maintained the largest transportation consultancy in Africa
working in 52 nations throughout the continent.
Reconnecting MOZAMBIQUE
Near the town Xai-Xai, in fertile Gaza province, the 190-meter, cable-supported Xai Xai Bridge
opened to traffic in 1964, serving the Maputo-Beira corridor, the main north-south artery in
Mozambique. The structure, crossing the Limpopo River 200 kilometers north of Maputo on National
Road 1, was built with prestressed concrete and composite steel girders, a reinforced concrete
deck, hinged pylons and reinforced concrete abutments. In 1989, however, a cable anchorage on the
Xai-Xai side failed sending two deck spans, 72 meters in length, into the river along with the
pylon on the Xai-Xai side. The Berger Group was selected by the Ministry of Public Works to
provide construction supervision services, including preparation of tendered documents,
assistance in bid evaluations and negotiations for the $5 million, OPEC-funded rehabilitation
project, which included replacement of the pylon on the Xai-Xai side and three central spans
totaling 110 meters. Additionally, new suspension cables were installed and new anchorage blocks
fabricated. The effort was completed in 24 months, on budget, despite major logistical and
security problems.
Adapting Designs in GUINEA
Nearly 25 years after the Berger Group first assisted in planning Guinea's highway modernization,
we continue to help the government implement its ambitious program. In early 1999, the Berger
Group was commissioned by the National Directorate of Rural Engineering, under a French
Development Aid program, to prepare designs and provide construction supervision for the
construction of eight bridges in Guinea's rugged western region. Given the region's isolation,
low traffic volumes, annual rainfall of 3,000 millimeters and limited availability of local
materials and skilled labor, the Team faced a challenging task in designing innovative, low-cost
structures.
Of the eight bridges, two are reinforced concrete and six are steel, which were chosen when
foundation soils were not sufficient to support heavier structures. The selected designs vary in
length from 30 to 135 meters with reinforced concrete abutments founded on shallow footings or
drilled piers. To reduce costs, two existing steel structures were cleaned and rehabilitated for
reuse and low-cost steel elements were shipped from France for on-site assembly.
For the Ministry of Transport and Public Works, Berger/Brokonsult designed two reinforced,
two-lane concrete bridges over the Bafing River between Mamou and Dabola. Because soils at the
site of Bafing I were unsuitable for heavy structures and low-cost solutions were mandated, the
Team selected a 30-meter, single-span, steel Mabey Johnson-type structure. The soil conditions
were better suited for heavy structures at the Bafing II site, and a 105-meter, nine-span
reinforced concrete structure was constructed. Both structures rest on reinforced concrete
abutments. The Japanese aid agency, OECF, funded the two bridges under the $105 million
upgrading of the 390-kilometer Mamou-Kankan road, for which the Berger Group also provided
construction supervision services. Under the same program, the Berger Group was selected to
supervise construction for the $8 million, 385-meter Niger and 25-meter Manie river bridges and
their access ramps along the 83-kilometer Kouroussa-Kankan link. In order to determine the
necessary construction parameters, the Berger Team carefully analyzed riverbank stability, river
bottom slope, fill materials and river currents. The studies revealed that huge pools of water
would form along the access ramps after rain. To reduce the potential for flooding, the Team
altered the original design raising the access ramps and bridges by 30 centimeters. The two
prestressed concrete structures will rest on reinforced concrete abutments and drilled piers.
Both the Niger, with 11 prestressed, dual-beam, concrete spans, and the Manie, a dual-beam,
single-span structure, will replace current ferry operations.
The Berger Group, in late 1998, was selected to supervise construction of the 270-meter, six-span
Fatala River Bridge. The site, at the narrowest point in the river, was selected by Berger
engineers in 1976 under our master plan developed at the onset of Guinea's highway modernization
program.
|